[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108237,783,1,"单选题","某混凝土工程计划进度与实际进度速度如下图所示，以总量的百分比计，该图表明本工程（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","第1周内实际进度超前5%",false,{"key":16,"text":17,"correct":18},"B","第3周内实际进度超前2%",true,{"key":20,"text":21,"correct":14},"C","第4周内实际进度拖后1%",{"key":23,"text":24,"correct":14},"D","第5周内实际进度拖后2%","考点:横道图比较法。选项A错误，第1周内实际进度拖后2%；选项C错误，第4周内实际进度拖后8%；选项D错误，第5天内实际进度拖后1%。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]