[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108234,783,1,"单选题","关于网络计划中工作实际进度偏差对后续工作及总工期影响的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际进度偏差大于总时差时，必然影响后续工作和总工期",true,{"key":16,"text":17,"correct":18},"B","实际进度偏差小于总时差而大于自由时差时，必然影响后续工作和总工期",false,{"key":20,"text":21,"correct":18},"C","实际进度偏差小于总时差和自由时差时，只影响总工期",{"key":23,"text":24,"correct":18},"D","实际进度偏差大于总时差时，只影响后续工作","考点:分析进度偏差对后续工作及总工期的影响。如果工作的进度偏差大于该工作的总时差，则此进度偏差必将影响其后续工作和总工期。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]