[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108233,783,1,"单选题","某工程进度计划执行过程中，发现某工作出现进度偏差，但该偏差未影响总工期，则说明该项工作的进度偏差（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","大于该工作的总时差",false,{"key":16,"text":17,"correct":18},"B","小于该工作的总时差",true,{"key":20,"text":21,"correct":14},"C","大于该工作的自由时差",{"key":23,"text":24,"correct":14},"D","小于该工作的自由时差","考点:分析进度偏差对后续工作及总工期的影响。进度偏差未超过总时差，偏差不影响总工期。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]