[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108232,783,1,"单选题","分析进度偏差对后续工作及总工期的影响时，应首先分析（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","出现进度偏差的工作是否为关键工作",true,{"key":16,"text":17,"correct":18},"B","进度偏差是否超过总时差",false,{"key":20,"text":21,"correct":18},"C","进度偏差是否超过自由时差",{"key":23,"text":24,"correct":18},"D","进度偏差的时距是否超过总时差","考点:分析进度偏差对后续工作及总工期的影响。分析进度偏差对后续工作和总工期的影响步骤如下：（1）分析出现进度偏差的工作是否为关键工作；（2）分析进度偏差是否超过总时差；（3）分析进度偏差是否超过自由时差。参见教材P103",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]