[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108231":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108231,783,1,"单选题","当利用S曲线比较工程项目的实际进度与计划进度时，如果检查日期实际进展点落在计划S曲线的左侧，则该实际进展点与计划S曲线在水平方向的距离表示工程项目（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实际超额完成的任务量",false,{"key":16,"text":17,"correct":14},"B","实际拖欠的任务量",{"key":19,"text":20,"correct":14},"C","实际进度拖后的时间",{"key":22,"text":23,"correct":24},"D","实际进度超前的时间",true,"考点:S曲线比较法。在S曲线图中，如果工程实际进展点落在计划S曲线左侧，表明此时实际进度比计划进度超前；如果工程实际进度点落在S计划曲线右侧，表明实际进度拖后。水平方向的差距表示超前的时间。参见教材P97",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]