[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108230,783,1,"单选题","在S曲线比较法中，当实际进展点落在计划S曲线左侧表示（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划进度估计错误",false,{"key":16,"text":17,"correct":14},"B","实际进度比计划进度落后",{"key":19,"text":20,"correct":14},"C","实际进度与计划进度相同",{"key":22,"text":23,"correct":24},"D","实际进度比计划进度超前",true,"考点:S曲线比较法。如果工程实际进展点落在计划S曲线左侧，表明此刻实际进度比计划进度超前；如果落在右侧，则表明此时实际进度拖后。参见教材P97。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]