[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108229":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108229,783,1,"单选题","某土方工程计划累计完成工程量的S曲线如下图所示，1～4天每天实际完成工程量分别为90m3、20m3、80m3、100m3，则第3天下班时该工程累计拖欠的工程量为（ ）m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",true,{"key":16,"text":17,"correct":18},"B","20",false,{"key":20,"text":21,"correct":18},"C","30",{"key":23,"text":24,"correct":18},"D","60","考点:S曲线比较法。第3天下班时刻该工程累计拖欠的工程量=计划完成工作量-实际完成工作量=200-90-20-80=10m3。参见教材P97",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]