[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108228,783,1,"单选题","S曲线比较法的横坐标表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单位时间",false,{"key":16,"text":17,"correct":18},"B","时间",true,{"key":20,"text":21,"correct":14},"C","累计完成任务量",{"key":23,"text":24,"correct":14},"D","单位时间完成的任务量","考点:S曲线比较法。S曲线比较法是以横坐标表示时间，纵坐标表示累计完成任务量，绘制一条按计划时间累计完成任务量的S曲线。参见教材P95",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]