[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108227":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108227,783,1,"单选题","在工程网络计划执行过程中，如果需要确定某工作进度偏差对总工期的影响，应根据（ ）的差值确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由时差与总时差",false,{"key":16,"text":17,"correct":18},"B","总时差与进度偏差",true,{"key":20,"text":21,"correct":14},"C","自由时差与进度偏差",{"key":23,"text":24,"correct":14},"D","时距与进度偏差","考点:分析进度偏差对后续工作及总工期的影响。在工程网络计划执行过程中，如果需要确定某工作进度偏差对总工期的影响，应根据总时差与进度偏差的差值确定。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]