[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108226":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108226,783,1,"单选题","当某项工作实际进度拖延的时间超过其总时差而需要对进度计划进行调整时，除需考虑总工期的限制条件外，还应考虑网络计划中（ ）的限制条件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","紧后工作",false,{"key":16,"text":17,"correct":14},"B","紧前工作",{"key":19,"text":20,"correct":21},"C","后续工作",true,{"key":23,"text":24,"correct":14},"D","关键工作","考点:进度计划的调整方法。当某项工作实际进度拖延的时间超过其总时差而需要对进度计划进行调整时，除需考虑总工期的限制条件外，还应考虑网络计划中后续工作的限制条件。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]