[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108225,783,1,"单选题","在建设工程进度计划的执行过程中，缩短某些工作的持续时间是调整建设工程进度计划的有效方法之一，这些被压缩的工作应该是关键线路和超过计划工期的非关键线路上（ ）的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","持续时间较长",false,{"key":16,"text":17,"correct":18},"B","直接费用率最小",true,{"key":20,"text":21,"correct":14},"C","所需资源有限",{"key":23,"text":24,"correct":14},"D","自由时差为零","考点:进度计划的调整方法。被压缩的工作应该是关键线路和超过计划工期的非关键线路上直接费用率最小的工作。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]