[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108220,783,1,"单选题","在建设工程网络计划实施中，某项工作实际进度拖延的时间超过其总时差时，如果不改变工作之间的逻辑关系，则调整进度计划的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","减小关键线路上该工作后续工作的自由时差",false,{"key":16,"text":17,"correct":18},"B","缩短该线路上该工作后续工作的持续时间",true,{"key":20,"text":21,"correct":14},"C","对网络计划进行“资源有限、工期最短”的优化",{"key":23,"text":24,"correct":14},"D","减小关键线路上该工作后续工作的总时差","考点:分析进度偏差对后续工作及总工期的影响。不改变工程项目中各项工作之间的逻辑关系，而通过采取增加资源投入、提高劳动效率等措施来缩短某些工作的持续时间，使工程进度加快，以保证按计划工期完成该工程项目。参见教材P103。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]