[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108219":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108219,783,1,"单选题","在匀速进展横道图中完成的任务量可用（ ）表示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实物工程量、劳动消耗量或费用支出",true,{"key":16,"text":17,"correct":18},"B","资金消耗量",false,{"key":20,"text":21,"correct":18},"C","日完成劳动量",{"key":23,"text":24,"correct":18},"D","单位时间完成任务量","考点:横道图比较法。完成的任务量可以用实物工程量、劳动消耗量或费用支出表示。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]