[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108218,783,1,"单选题","某钢筋工程计划用7周完成，每周计划和实际累计完成情况如图所示。关于该工程进度比较结果的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际开始时间晚于计划开始时间1周",false,{"key":16,"text":17,"correct":18},"B","第2周末实际进度比计划进度拖后5%",true,{"key":20,"text":21,"correct":14},"C","第4周内计划完成的任务量为28%",{"key":23,"text":24,"correct":14},"D","第5周内实际任务量比计划任务量拖后6%","考点:横道图比较法。选项A，实际开始时间晚于计划开始时间不到1周；选项C，第4周内计划完成的任务量为10%；选项D，第5周内实际任务量比计划任务量拖后8%。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]