[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108217,783,1,"单选题","在利用S曲线比较建设工程实际进度与计划进度时，如果检查日期实际进展点落在计划S曲线的左侧，则该实际进展点与计划S曲线在纵坐标方向的距离表示该工程（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实际进度超前的时间",false,{"key":16,"text":17,"correct":18},"B","实际超额完成的任务量",true,{"key":20,"text":21,"correct":14},"C","实际进度拖后的时间",{"key":23,"text":24,"correct":14},"D","实际拖欠的任务量","考点:S曲线比较法。如果检查日期实际进展点落在计划S曲线的左侧，则该实际进展点与计划S曲线在纵坐标方向的距离表示该工程实际超额完成的任务量。参见教材P96。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]