[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108215":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":22},1108215,783,1,"单选题","检查某工程的实际进度后，绘制的前锋线如图所示，在原计划工期不变的情况下，H工作尚有总时差（ ）天。",[11,15,19],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","2",false,{"key":20,"text":21,"correct":18},"C","3","考点:前锋线比较法。H工作尚有总时差1天。参见教材P101。",{"id":6,"name":24,"category":25,"favorite":26},"目标控制（土木建筑）","建筑工程",0]