[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108214,783,1,"单选题","对某网络计划在某时刻进行检查，发现工作A尚需作业天数为6天，该工作到计划最迟完成时间尚余5天，则该工作（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可提前1天完成",false,{"key":16,"text":17,"correct":14},"B","正常",{"key":19,"text":20,"correct":21},"C","影响总工期1天",true,{"key":23,"text":24,"correct":14},"D","影响总工期3天","考点:列表比较法。如果某工作尚需作业天数超过其最迟完成时间尚需的天数，那么就会影响总工期，其值为二者之差。工作A尚需作业天数为6天，该工作到计划最迟完成时间尚需5天，说明该工作拖后超过了总时差1天，影响总工期1天。参见教材P102。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]