[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108212":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":23},1108212,783,1,"单选题","根据双代号时标网络计划的实际进度前锋线，（ ）工作将影响工期。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","C",false,{"key":16,"text":17,"correct":14},"B","D",{"key":13,"text":19,"correct":20},"E",true,{"key":17,"text":22,"correct":14},"G","考点:前锋线比较法。工作E进度拖后两天，其总时差为1天，所以影响工期1天。参见教材P101。",{"id":6,"name":25,"category":26,"favorite":27},"目标控制（土木建筑）","建筑工程",0]