[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108208,783,1,"单选题","某工作的实际进度与计划进度如下图所示，错误的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","第4周末本工作实际完成的任务量小于计划任务量",false,{"key":16,"text":17,"correct":14},"B","本工作未按计划完成",{"key":19,"text":20,"correct":14},"C","第3周停工半周",{"key":22,"text":23,"correct":24},"D","第4～5周实际进度为匀速进展",true,"考点:横道图比较法。本工作在第1周停工半周，不是匀速进展。至检查日期实际完成了70%，而计划完成为80%，所以未按计划完成。第3周有一半空白，表示停工半周。第4周实际完成18%，第5周实际完成20%，所以不是匀速进展。第4周末本工作计划完成任务量为60%，实际完成工作量50%。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]