[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108206":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108206,783,1,"单选题","在建设工程进度计划的实施过程中，监理工程师控制进度的关键步骤是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","加工处理收集到的实际进度数据",false,{"key":16,"text":17,"correct":14},"B","调查分析进度偏差产生的原因",{"key":19,"text":20,"correct":14},"C","实际进度与计划进度的对比分析",{"key":22,"text":23,"correct":24},"D","跟踪检查进度计划的执行情况",true,"考点:进度计划执行中的跟踪检查。对进度计划的执行情况进行跟踪检查是计划执行信息的主要来源，是进度分析和调整的依据，也是进度控制的关键步骤。参见教材P90。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]