[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108202,783,1,"单选题","不属于监理工程师全面、准确地掌握进度计划的执行情况，要做的工作的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","定期收集进度报表资料",false,{"key":16,"text":17,"correct":14},"B","现场实地检查工程进展情况",{"key":19,"text":20,"correct":21},"C","实际进度数据的加工处理",true,{"key":23,"text":24,"correct":14},"D","定期召开现场会议","考点:进度监测的系统过程。为了全面、准确地掌握进度计划的执行情况，监理工程师应认真做好以下三方面工作：定期收集进度报表资料；现场实地检查工程进展情况；定期召开现场会议。参见教材P90。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]