[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108174":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108174,783,1,"单选题","关于净现值指标的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该指标能够直观地反映项目在运营期内各年的经营成果",false,{"key":16,"text":17,"correct":14},"B","该指标可直接用于不同寿命期互斥方案的比选",{"key":19,"text":20,"correct":14},"C","该指标小于零时，项目在经济上可行",{"key":22,"text":23,"correct":24},"D","该指标大于等于零时，项目在经济上可行",true,"考点:财务分析主要指标的计算。选项A错误，净现值不能直接说明在项目运营期各年的经营成果；选项B错误，在互斥方案评价时，净现值必须慎重考虑互斥方案的寿命，如果互斥方案寿命不等，必须构造一个相同的分析期限，才能进行方案比选；选项C错误，当方案的NPV≥0时，说明该方案能满足基准收益率要求的盈利水平，故在经济上是可行的；当方案的NPV＜0时，说明该方案不能满足基准收益率要求的盈利水平，故在经济上是不可行的。参见教材P87。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]