[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108155":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108155,783,1,"单选题","关于净年值指标的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该指标全面考虑了项目在整个计算期内的经济状况",true,{"key":16,"text":17,"correct":18},"B","该指标需要考虑计算期时间长短的差别及影响",false,{"key":20,"text":21,"correct":18},"C","该指标反映了项目投资中单位投资的使用效率",{"key":23,"text":24,"correct":18},"D","该指标直接说明了在项目运营期各年的经营成果","考点:财务分析主要指标的计算。选项B错误，净年值指标无需考虑计算期的时间长短；选项C错误，净年值不能反映单位投资的使用效率；选项D错误，净年值综合考虑建设期和运营期，但其均值不能直接说明在项目运营各年的经营成果。参见教材P89。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]