[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108153":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108153,783,1,"单选题","某建设项目，第1～3年每年年末投入建设资金500万元，第4～8年每年年末获得利润800万元，则该项目的静态投资回收期为（ ）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3.87",false,{"key":16,"text":17,"correct":18},"B","4.88",true,{"key":20,"text":21,"correct":14},"C","4.90",{"key":23,"text":24,"correct":14},"D","4.96","考点:财务分析主要指标的计算。根据静态投资回收期的计算公式，并考虑整个计算期（3年建设期+4年运营期），运营期每年获得800万元利润，收回1500万元的投入，至少需要2年。于是，Pt=5-1+700／800=4.88（年）。当然，某项目的投资回收期，短于基准投资回收期（Pe），说明其经济上可行。参见教材P86。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]