[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108152":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108152,783,1,"单选题","下列关于项目盈利能力分析的说法中，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","若财务内部收益率大于或等于基准收益率，方案可行",false,{"key":16,"text":17,"correct":18},"B","若投资回收期大于或等于行业标准投资回收期，方案可行",true,{"key":20,"text":21,"correct":14},"C","若财务净现值大于或等于零，方案可行",{"key":23,"text":24,"correct":14},"D","若总投资收益率高于同行业收益率参考值，方案可行","考点:财务分析主要指标的计算。根据建设项目财务评价各项指标（盈利能力分析）的判别准则，若投资回收期小于或等于行业标准投资回收期，则该方案可行。因此，选项B说法错误。参见教材P84。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]