[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108150,783,1,"单选题","某项目采用试差法计算内部收益率时，发现折现率为15%、18%和20%时，所对应的净现值分别为150万元、30万元和-10万元。因此，该项目的内部收益率应为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","17.50%",false,{"key":16,"text":17,"correct":18},"B","19.50%",true,{"key":20,"text":21,"correct":14},"C","19.69%",{"key":23,"text":24,"correct":14},"D","20.16%","考点:财务分析主要指标的计算。通过分析净现值正负交替、最为接近的两组数据发现，折现率=18%，其相对应的净现值NPV1＝30万元>0；折现率=20%，净现值NPV2＝-10 当然，内部收益率大于基准收益率，该方案经济上可行。参见教材P89。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]