[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108145":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108145,783,1,"单选题","下列关于经济费用效益分析的内容表述不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经济费用效益分析应采用以影子价格体系为基础的预测价格，考虑价格总水平变动因素",true,{"key":16,"text":17,"correct":18},"B","项目经济费用效益分析采用社会折现率对未来经济效益和经济费用流量进行折现",false,{"key":20,"text":21,"correct":18},"C","项目的所有效益和费用一般均应在共同的时点基础上予以折现",{"key":23,"text":24,"correct":18},"D","项目的所有效益和费用包括不能货币化的效果","考点:项目经济分析。经济费用效益分析应采用以影子价格体系为基础的预测价格，不考虑价格总水平变动因素。项目经济费用效益分析采用社会折现率对未来经济效益和经济费用流量进行折现。项目的所有效益和费用（包括不能货币化的效果）一般均应在共同的时点基础上予以折现。参见教材P93。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]