[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108059,783,1,"单选题","按我国现行建设工程投资的构成，建设工程总投资包括固定资产投资和（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设期利息",false,{"key":16,"text":17,"correct":14},"B","基本预备费",{"key":19,"text":20,"correct":14},"C","涨价预备费",{"key":22,"text":23,"correct":24},"D","流动资产投资",true,"考点:我国现行建设工程投资构成。建设工程总投资包括固定资产投资和流动资产投资。选项ABC属于固定资产投资。参见教材P11。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]