[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108055":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108055,783,1,"单选题","根据世界银行和国际咨询工程师联合会建设工程投资的构成，服务性建筑费用属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目直接建设成本",true,{"key":16,"text":17,"correct":18},"B","项目间接建设成本",false,{"key":20,"text":21,"correct":18},"C","应急费",{"key":23,"text":24,"correct":18},"D","建设成本上升费","考点:世界银行和国际工程师联合会建设工程投资构成。服务性建筑费用属于项目建设直接成本。参见教材P12。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]