[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108051":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108051,783,1,"单选题","若进口设备采用装运港船上交货价，则卖方的责任有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","负责租船订舱，支付运费",false,{"key":16,"text":17,"correct":14},"B","负责办理保险及支付保险费",{"key":19,"text":20,"correct":14},"C","办理在目的港的进口手续",{"key":22,"text":23,"correct":24},"D","负责货物装船前的一切风险和费用",true,"考点:设备购置费的组成与计算。进口设备采用不同的交货方式，导致买卖双方的责任、风险以及费用构成等不同。装运港船上交货类，卖方负责货物装船前的一切风险和费用。参见教材P28。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]