[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108038":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1108038,783,1,"单选题","国际工程项目建筑安装工程费用的组成中，可以计入直接费中人工费、材料设备和机械施工费的保险费不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工机械保险",false,{"key":16,"text":17,"correct":14},"B","材料设备运输保险",{"key":19,"text":20,"correct":14},"C","人身意外保险",{"key":22,"text":23,"correct":24},"D","机动车辆保险",true,"考点:国际工程项目建筑安装工程费用的构成。国际工程中的保险项目一般有工程保险、第三者责任保险、机动车辆保险、人身意外保险、材料设备运输保险、施工机械保险等，其中后三项保险的费用已分别计入直接费中的人工、材料设备和机械使用费。参见教材P26。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]