[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108035":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108035,783,1,"单选题","设备的无负荷联动试运转费用属于建设工程总投资中的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备及工器具购置费",false,{"key":16,"text":17,"correct":18},"B","建筑安装工程费",true,{"key":20,"text":21,"correct":14},"C","工程建设其他费用",{"key":23,"text":24,"correct":14},"D","预备费","考点:工程建设其他费用。联合试运转费不包括应由设备安装工程费开支的单台设备调试费及无负荷联动试运转费用。从而得知无负荷联动试运转费用属于设备安装工程费。建筑安装工程费中包含设备安装工程费。参见教材P34。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]