[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108031,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500－2013的规定，已完工程及设备保护费是指在（ ），对已完工程及设备进行保护所需的费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工过程中",false,{"key":16,"text":17,"correct":14},"B","施工结束后",{"key":19,"text":20,"correct":21},"C","竣工验收前",true,{"key":23,"text":24,"correct":14},"D","竣工验收后","考点:按造价形成划分的建筑安装工程费用项目组成。已完工程及设备保护费是指竣工验收之前，对已完工程及设备进行保护所需费用。参见教材P18。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]