[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108029":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108029,783,1,"单选题","按造价形成划分的建筑安装工程费，（ ）是指在冬期或雨期施工需增加的临时设施，防滑，排除雨雪、人工及施工机械效率降低等的费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","保暖费",false,{"key":16,"text":17,"correct":14},"B","特殊情况施工增加费",{"key":19,"text":20,"correct":21},"C","冬雨期施工增加费",true,{"key":23,"text":24,"correct":14},"D","寒冷地区施工增加费","考点:按造价形成划分的建筑安装工程费用项目组成。冬雨期施工增加费是指在冬期或雨期施工需增加的临时设施，防滑，排除雨雪、人工及施工机械效率降低等费用。参见教材P18。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]