[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108024":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1108024,783,1,"单选题","按照费用构成要素划分的建筑安装工程费用项目，下列费用中，属于人工费中奖金的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","劳动竞赛奖",true,{"key":16,"text":17,"correct":18},"B","停工学习薪酬",false,{"key":20,"text":21,"correct":18},"C","赶工费",{"key":23,"text":24,"correct":18},"D","集体福利费","考点:按费用构成要素划分的建筑安装工程费用项目组成。奖金是指对超额劳动和增收节支支付给个人的劳动报酬。如节约奖、劳动竞赛奖等。参见教材P13。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]