[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108016,783,1,"单选题","根据现行规定，因病假、停工学习等原因，按计时工资标准或计时工资标准的一定比例支付的工资，属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计时工资或计件工资",false,{"key":16,"text":17,"correct":18},"B","特殊情况下支付的工资",true,{"key":20,"text":21,"correct":14},"C","劳动保险和职工福利费",{"key":23,"text":24,"correct":14},"D","劳动保护费","考点:按费用构成要素划分的建筑安装工程费用项目组成。根据“44号文”，因病假、停工学习等原因，按计时工资标准或其一定比例支付的工资，属于特殊情况下支付的工资。至于劳动保险和职工福利费、劳动保护费均属企业管理费，并各有所指。参见教材P13。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]