[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1108011,783,1,"单选题","某工程的分部分项工程费为400万元（不含可抵扣进项税款）。其中，定额人工费为100万元，措施项目费为分部分项工程费的5%，其他项目费为15万元，企业管理费费率为30%，利润率为5%，规费费率为8%，增值税率为9%。则该工程的招标控制价为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","446.00",false,{"key":16,"text":17,"correct":14},"B","458.11",{"key":19,"text":20,"correct":21},"C","482.87",true,{"key":23,"text":24,"correct":14},"D","500.12","考点:建筑安装工程计价程序。该工程的措施项目费=400×5%=20（万元）； 规费=100（定额人工费）×8%=8（万元）；税金=（分部分项工程费+措施项目费+其他项目费+规费）×9%=（400+20+15+8）×9%=39.87（万元）。该工程的招标控制价=400+20+15+8+39.87=482.87（万元）。参见教材P23～25。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]