[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1108002":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1108002,783,1,"单选题","某项目的建筑安装工程费为2000万元，设备购置费为600万元，工程建设其他费为100万元，建设期利息为60万元，铺底流动资金为160万元。若基本预备费的费率为10%，则基本预备费为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","260",false,{"key":16,"text":17,"correct":18},"B","270",true,{"key":20,"text":21,"correct":14},"C","276",{"key":23,"text":24,"correct":14},"D","292","考点:预备费。基本预备费的计算基数为建筑安装工程费、设备购置费、工程建设其他费的三项之和。于是，该项目的基本预备费=（2000+600+100）×10%=270（万元）。参见教材P35。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]