[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107978,783,1,"单选题","根据设计要求，在施工过程中对某屋架结构进行破坏性试验，以提供和验证设计数据，则该项费用应在（ ）中支出。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","研究试验费",true,{"key":16,"text":17,"correct":18},"B","临时设施费",false,{"key":20,"text":21,"correct":18},"C","建设单位管理费",{"key":23,"text":24,"correct":18},"D","勘察设计费","考点:工程建设其他费用。无论是自行研究，还是委托研究，通过破坏性试验提供和验证的设计数据所需的费用，均属建设单位的研究试验费（注意它与企业管理费中的检验试验费的区别）。参见教材P33。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]