[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107977":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107977,783,1,"单选题","某新建化工项目，建设期为3年，共向银行贷款1500万，贷款情况为：第一年，400万元；第二年，800万元；第三年，300万元，每年贷款资金均衡投入。年利率为10%，则计算建设期利息后的本利和为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1650.00",false,{"key":16,"text":17,"correct":18},"B","1747.20",true,{"key":20,"text":21,"correct":14},"C","1810.00",{"key":23,"text":24,"correct":14},"D","1996.50","考点:建设期利息。第一年应计利息：1\u002F2×400×10%＝20.00（万元）；第二年应计利息：（400＋20＋1\u002F2×800）×10%＝82.00（万元）；第三年应计利息：（400＋20＋800＋82＋1\u002F2×300）×10%＝145.20（万元）；建设期利息合计＝20＋82＋145.2＝247.20（万元）；本利和＝1500＋247.20＝1747.20（万元）。参见教材P36。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]