[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107956":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107956,783,1,"单选题","建筑安装工程费中工伤保险费的计算基础是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定额直接费",false,{"key":16,"text":17,"correct":18},"B","定额人工费",true,{"key":20,"text":21,"correct":14},"C","定额人工费和机械费",{"key":23,"text":24,"correct":14},"D","定额人工费和材料费","考点:建筑安装工程费用计算方法。工伤保险费的计算基础是定额人工费。参见教材P21。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]