[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107953,783,1,"单选题","在施工过程中，施工企业完成建设单位提出的施工图纸以外的零星项目或工作所需的费用，属于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","措施项目费",false,{"key":16,"text":17,"correct":14},"B","总承包服务费",{"key":19,"text":20,"correct":21},"C","计日工",true,{"key":23,"text":24,"correct":14},"D","暂列金额","考点:建筑安装工程费用组成与计算（按照工程造价形成）。根据“44号文”的规定，施工企业完成建设单位提出的施工图纸以外的零星项目或工作所需的费用，属于计日工。参见教材P19。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]