[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107943,783,1,"单选题","根据《建筑安装工程费用组成》的规定，可以利用综合单价法计算的措施项目费，包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安全文明施工费",false,{"key":16,"text":17,"correct":14},"B","夜间施工增加费",{"key":19,"text":20,"correct":14},"C","已完工程及设备保护费",{"key":22,"text":23,"correct":24},"D","脚手架工程费",true,"考点:建筑安装工程费用计算方法。大型机械设备进出场及安拆费、脚手架工程费可以利用综合单价法计算费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]