[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107942":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107942,783,1,"单选题","下列世界银行和国际咨询工程师联合会建设工程投资构成中不属于项目间接建设成本的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","开工试车费",false,{"key":16,"text":17,"correct":14},"B","差旅费",{"key":19,"text":20,"correct":14},"C","地方关税",{"key":22,"text":23,"correct":24},"D","建筑保险",true,"考点:世界银行和国际咨询工程师联合会建设工程投资构成。选项D，建筑保险属于项目直接建设成本中的其他当地费用。参见教材P12。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]