[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107941":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107941,783,1,"单选题","在国外项目总建设成本的构成中，从估算日期到工程结束时发生的材料和设备价格上涨，应当列入（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目间接建设成本",false,{"key":16,"text":17,"correct":14},"B","未明确项目准备金",{"key":19,"text":20,"correct":14},"C","不可预见准备金",{"key":22,"text":23,"correct":24},"D","建设成本上升费",true,"考点:世界银行和国际咨询工程师联合会建设工程投资构成。根据世界银行和国际咨询工程师联合会等规定，项目总建设成本（相当于国内的建设工程总投资）包括项目直接建设成本、项目间接建设成本、应急费和建设成本上升费。其中，题干所述应当属于建设成本上升费（选项D）。参见教材P13。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]