[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107937,783,1,"单选题","在初步设计阶段，影响项目投资的可能性是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0%～95%",false,{"key":16,"text":17,"correct":14},"B","5%～35%",{"key":19,"text":20,"correct":14},"C","50%～75%",{"key":22,"text":23,"correct":24},"D","75%～95%",true,"考点:投资控制的重点。在初步设计阶段，影响项目投资的可能性为75%～95%；在技术设计阶段，影响项目投资的可能性为35%～75%；在施工图设计阶段，影响项目投资的可能性则为5%～35%。参见教材P4。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]