[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107936,783,1,"单选题","某项目的建筑安装工程投资为1000万元，基本预备费为100万元，设备购置费为300万元，物价上涨费预备费为20万元，贷款利息为50万元，则上述投资中属于静态投资的因素总和为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1050",false,{"key":16,"text":17,"correct":14},"B","1450",{"key":19,"text":20,"correct":21},"C","1400",true,{"key":23,"text":24,"correct":14},"D","1380","考点:建设工程项目投资的概念。静态投资是由建筑安装工程费、设备及工器具购置费、工程建设其他费和基本预备费组成。动态投资部分是指在建设期内，因建设期利息和国家新批准的税费、汇率、利率变动以及建设期价格变动引起的固定资产投资增加额，包括涨价预备费和建设期利息。所以本题静态投资为：1000+100+300=1400（万元）。参见教材P1。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]