[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107930,783,1,"单选题","下列属于我国项目监理机构在施工阶段投资控制的主要工作的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分析可能发生索赔的原因，制定防范对策",false,{"key":16,"text":17,"correct":14},"B","对拟建项目进行财务评价",{"key":19,"text":20,"correct":21},"C","对已完工程量进行偏差分析",true,{"key":23,"text":24,"correct":14},"D","审查设计单位提交的设计成果","考点:我国监理机构在施工阶段进行投资控制的主要工作。在施工阶段投资控制的主要工作包括：进行工程计量和付款签证；对完成工程量进行偏差分析；审核竣工结算款；处理施工单位提出的工程变更费用；处理费用索赔。参见教材P8。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]