[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107925,783,1,"单选题","建设工程设计方案选择和进行初步设计应依据（ ）设置投资控制目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资估算",true,{"key":16,"text":17,"correct":18},"B","设计概算",false,{"key":20,"text":21,"correct":18},"C","施工图预算",{"key":23,"text":24,"correct":18},"D","建安工程承包合同价","考点:投资控制的目标。投资估算应是建设工程设计方案选择和进行初步设计的投资控制目标。参见教材P4。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]