[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107921":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107921,783,1,"单选题","项目监理机构在施工阶段进行投资控制有多种措施，下列选项属于合同措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对发包人原因导致承包人机械闲置，予以费用补偿审核",true,{"key":16,"text":17,"correct":18},"B","严格控制设计变更",false,{"key":20,"text":21,"correct":18},"C","审核竣工结算",{"key":23,"text":24,"correct":18},"D","改进施工工艺和施工技术","考点:投资控制的措施。项目监理机构在施工阶段进行投资控制的合同措施有：（1）做好工程施工记录，保存各种文件图纸，特别是注有实际施工变更情况的图纸，注意积累素材，为正确处理可能发生的索赔提供依据。参与处理索赔事宜。（2）参与合同修改、补充工作，着重考虑它对投资控制的影响。选项C属于经济措施；选项BD属于进度控制中的技术措施。参见教材P6。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]